What this offence actually covers
Decommissioning an economic facility — the final shutdown and dismantling of a plant, workshop, warehouse, quarry, tank farm or any other facility used for economic activity — is not only a technical and accounting exercise. Georgian law expects environmental requirements to be observed at this last stage of a facility's life cycle as well, because closure is exactly the moment when residual material, demolished structures, contaminated soil or liquids are most likely to be left behind unattended. Article 69⁵ of the Administrative Offences Code of Georgia addresses breaches committed at that stage.
In practice this means that closing a facility is a self-contained legal process with its own completion, not merely the moment activity stops. Where something goes wrong in that process, liability can arise even though the plant itself is no longer operating.
What Article 69⁵ says and what it costs
The wording is short. A breach of environmental requirements during the decommissioning of an economic facility carries a fine of two hundred to four hundred GEL. That is the only sanction the article provides: the lower limit is 200 GEL and the upper limit is 400 GEL. The article provides for no confiscation and for no withdrawal of the right to carry out an activity.
A second feature matters just as much. Article 69⁵ is a blanket provision — it does not itself list the "environmental requirements" it protects, because those are set out in other acts of environmental legislation. So before this article can be said to have been breached, the specific requirement written into some other act has to be located. What the protocol must contain is not fixed by Article 69⁵ — that is governed by other provisions of the Code; the practical question for you is which rule you were required to observe during the decommissioning.
Who is held liable
The article reaches whoever was under a duty to carry out the decommissioning, or who in fact carried it out: the owner of the facility, the party holding it in use, the client who commissioned the works, or the contractor who performed them. Where a third party dismantled the site under contract, the decisive question becomes which of them owed the particular environmental requirement in question. This is not a formality. It is the point at which it most often emerges that the protocol names the wrong subject, and that the penalty is being imposed on a party who never held the obligation at all.

