Grounds for Claiming Contractual Damages
A breach of a contractual relationship does not always end with the debtor's performance of the obligation itself — the creditor often has additional loss, and the Civil Code of Georgia regulates a complete arsenal for claiming its compensation. Article 394 creates the general ground: upon the debtor's breach of the obligation, the creditor may demand compensation for the damage caused thereby. This rule does not operate only where the debtor bears no liability for the breach — that is, where the breach is not the debtor's fault and the law releases the debtor.
On this page we explain the five central questions of a contractual-damages claim: the setting of an additional period in case of delay, the right to compensation for damage caused by delay, the compensation of lost profit, the limits of monetary compensation for non-pecuniary damage, and the court's power to reduce a contractual penalty.
The Additional Period and the Activation of the Claim
The second part of Article 394 establishes the practical mechanism of delay: upon the debtor's delay, the creditor may set the debtor a period necessary for the performance of the obligation. If the debtor fails to perform within that period as well, the creditor is entitled, instead of the performance of the obligation, to demand compensation for the damage. This means the law first demands a warning period and only after its frustration opens the way to a claim for compensation — instead of performance.
An exception is defined too: setting an additional period is unnecessary where it is evident that it would produce no result, or where special circumstances exist which, considering the interests of both parties, justify the immediate application of the claim for compensation. In practice this means that where the debtor's conduct makes it clear performance is no longer intended, the creditor is not obliged to wait out the formal additional period.
Damage Caused by Delay and Lost Profit
Article 404 gives the creditor the right to claim compensation for the damage caused by the delay. This norm matters because it separately analyzes the consequences of lateness: even if the debtor ultimately performs, the loss caused by the delay — for example, in the form of halted production or the cost of substitution — becomes a separate object of the claim.
Nor is compensation exhausted by the actually incurred pecuniary loss. Under Article 411, damage must be compensated also for lost income. Lost income is the income the person did not receive and would have received had the obligation been duly performed. The substantiation of the amount of lost profit often remains the contested question: the creditor must show a convincing computation — both from historical data and market analysis — that the income would genuinely have been received, and building this claim is precisely counsel's task.
Non-Pecuniary Damage and the Reduction of Penalties
In contractual relationships, monetary compensation for non-pecuniary damage may be claimed only in cases precisely defined by law, in the form of reasonable and just compensation — so provides the first part of Article 413. The exception is bodily injury or harm to health: there the victim may claim compensation for non-pecuniary damage as well. Thus, as a general rule, a monetary claim for moral damage in a contractual dispute is constrained, and every such attempt must rest on grounds contemplated by law.
Article 420 is important for both sides: the court may, considering the circumstances of the case, reduce a disproportionately high contractual penalty. This norm creates a balance: a penalty agreed in advance is a lawful instrument, but its excess becomes the object of the court's correction. For the debtor it is the possibility of reduction; for the creditor, a warning that the penalty ceiling must correspond to reality.
The Practical Stages of Building the Claim
A contractual-damages claim is a structure built on three elements: breach of the obligation, damage, and the causal link between them. The creditor must substantiate each element with documents: the obligation established by the contract and its breach, evidence describing the damage and the computations, and the logic of the connection between the breach and the loss. The debtor, in turn, may oppose each link of this chain — by denying the breach, invoking a ground of release from liability, criticizing the amount of the damage, or severing the causal link.
Managing time is also decisive: setting the additional period, fixing its frustration, and preparing the computation of lost profit all occur in the pre-suit stage, and the earlier the creditor begins consolidating the evidence, the better protected the position in court.
Frequently Asked Questions
What may the creditor claim on a breach?
Compensation for the damage caused by the breach — by force of Article 394, where the debtor bears liability for the breach; in case of delay, also the damage caused by the delay under Article 404.
Is setting an additional period mandatory?
As a rule yes — the creditor sets in writing a period necessary for performance and only after its frustration claims compensation instead of performance; the exceptions are the evident futility of the period or special circumstances.
May lost profit be claimed?
Yes — damage is compensated not only for the actual loss but also for lost income: the income the creditor would have received upon due performance.
When does the court reduce a penalty?
Where it is disproportionately high — Article 420 entitles the court to reduce it considering the circumstances of the case.
How We Help on Legal.ge
The attorneys at Legal.ge represent both sides in contractual-damages cases: we prepare demands and suits with the full structure of the damage — actual loss, lost profit and the consequences of delay; and, conversely, in the debtor's position we verify every element of the damage and substantiate the reduction of the penalty.
If you have suffered loss through a breach of contract or face a damages claim, contact us at Legal.ge — we will assess the case under the exact norms of the Civil Code and build an effective position.

