The Project Delay Suit: The Court Route and Its Construction
When a delayed project can no longer be resolved by negotiation, the remaining route is the court, and the strength of the suit depends on its construction. The Civil Code assembles a full ladder for a delay suit: the setting of an additional period and refusal, the claim of damages, the parties’ rights of termination, interest, and limitation. Each step requires its own conditions, and skipping steps makes the suit untenable.
The structure of the suit is assembled according to this ladder: first the breach and its character are fixed; then the documentation of the additional period or warning is presented; then the damage, actual loss and lost income; and finally the formulation of the claim: performance, damages, interest or the consequences of refusal. The evidence block is built by the same logic: the schedule and its amendments, the letters on the additional period or warning, the acts of the actual volume of performance and the damage calculations must be linked to one another consistently. The court checks how far each claim corresponds to this chain, and a broken chain weakens the whole suit.
The Additional Period and Refusal of the Contract
The first step of the suit is Article 405 of the Civil Code: where one party to a contract breaches an obligation arising from a bilateral contract, the other party may refuse the contract after the fruitless expiry of an additional period determined by it for the performance of the obligation. Where, from the character of the breach, an additional period does not apply, a warning is equated to the determination of an additional period. Where the obligation is breached only in part, the creditor may refuse the contract only if performance of the remaining part has lost its interest for it. The same article provides that an additional period or warning is not necessary where it is evident that it will have no result, where the creditor made continuation of the relationship conditional on timely performance, or where, on special grounds and considering the interests of both parties, immediate termination of the contract is justified. Refusal is inadmissible where the breach is insignificant, where the creditor itself is responsible for the breach, or where the claim is opposed by a counter-performance which the debtor has already submitted or will submit immediately.
The Claim of Damages
The second step is damage. Under Article 394 of the Civil Code, on breach of the obligation by the debtor the creditor may claim compensation for the damage thereby caused; this rule does not apply where the debtor bears no responsibility for the breach. On delay of the term, the creditor may set the debtor a necessary time for performance, and if the debtor does not perform within that time either, the creditor may claim damages instead of performance. Determining an additional period is not necessary where it is evident that it will have no result, or where special circumstances, considering the interests of both parties, justify the immediate claim of damages.
The Parties’ Termination Rights Before Completion
The construction relationship also has special rules. Under Article 636 of the Civil Code, the customer has the right to refuse the contract at any time before completion of the work, but must reimburse the contractor for the performed work and the damage caused by the termination. From the contractor’s side, Article 637 of the Civil Code is strict: the contractor may terminate the contract before completion of the work only in such a way that the customer is able to obtain the service otherwise, except where a significant ground for termination exists; in that case the duty to compensate damage is excluded. In the suit, the correct application of these two rules determines whose termination was competent and what consequences followed it.
Interest and Limitation
For monetary claims, Article 403 of the Civil Code sets interest: a debtor who delays the payment term of a monetary sum must pay for the delayed time the interest determined by the parties’ agreement, unless the creditor may demand more on another basis. The limitation regime is defined by Article 129 of the Civil Code: the limitation period for contractual claims is three years, and for contractual claims connected with immovables six years. A construction dispute is mostly connected with an immovable, so the six-year period often applies, but the character of each claim is qualified separately.
Frequently Asked Questions
Below are the answers to the questions most frequently asked about delay suits.
What is the additional period and when is it needed?
On breach, the other party may demand performance within an additional period and refuse the contract after its fruitless expiry. It is unnecessary where it is evidently futile or where special grounds justify immediate termination.
May the customer refuse at any time?
Yes, before completion of the work, but the customer must reimburse the performed work and the damage caused by the termination.
When may the contractor terminate?
Only so that the customer can obtain the service otherwise. Where a significant ground exists, termination is possible and compensation is excluded.
How is damage assessed on delay?
On breach the creditor may claim the caused damage. On delay, a necessary time may be set, and after its fruitless expiry damages may be claimed instead of performance.
What limitation periods apply to such claims?
Contractual claims carry three years, and claims connected with immovables six years.
How We Help on Legal.ge
Our team builds delay suits from the preparation stage onward: we structure the correspondence on additional periods and warnings, assess damage and lost income, apply the interest rules and maintain limitation control under the three-year and six-year regimes. Contact us on Legal.ge so that a delay suit is built completely, with every step of the ladder.
