Cost Estimate Overruns and Their Consequences
One of the most common grounds of construction disputes is the overrun of the cost estimate. Article 631 regulates this situation clearly: if the contractor significantly exceeds the approximate cost estimate, it may claim only the agreed remuneration, except where the excess could not have been foreseen in advance. This rule places the risk of overspending on the contractor and obliges it to plan precisely.
Where the cost estimate increases in a way that could not have been foreseen at the conclusion of the contract, the contractor must notify the customer immediately. If the customer terminates the contract because of the increase in the estimate, it is obliged to pay for the work performed according to the approximate cost estimate. A timely and documented notice of the overrun is in this situation the foundation of the contractor's position, and its absence may cost the contractor the entire excess.
The Customer's Inaction and Compensation of Loss
The second flashpoint of disputes is the customer's conduct. Under Article 633, the contractor may claim compensation of loss if the customer does not accept the completed work. The customer is obliged to compensate the loss also where it fails to perform an action necessary for the performance of the work — inaction, too, engages responsibility.
The amount of compensation is determined, on the one hand, according to the duration of the delay and the amount of the remuneration and, on the other hand, according to what the contractor would have earned by using its labour otherwise, had the customer not exceeded the term. This formula ties the loss to the contractor's actual detriment, and its calculation always rests on evidence — records of the delay, of the idle capacity and of the alternative uses of the workforce.
Termination by Either Party
Article 636 gives the customer a broad right: to refuse the contract at any time before completion of the work, but it must compensate the contractor for the work performed and for the loss caused by the termination. The unrestricted right of refusal creates flexibility, yet its price — compensation of the performed work and of the resulting loss — must be calculated before the decision is taken.
For the contractor the rule is stricter: under Article 637, the contractor may discontinue the contract before completion only in such a way that the customer is able to obtain the service otherwise, unless a significant ground for the discontinuation exists; in the latter case the duty to compensate loss is excluded. The existence of a significant ground must be established by the contractor and, if necessary, upheld in court.


