Legal.geLegal.geLegal.ge
SpecialistsCompaniesLibraryBlog
More
AboutPricingContact
LegalTools
Loading accountLog in
AboutSpecialistsCompaniesLibraryBlogPricingContact
LegalTools
Loading accountLog in
Legal.ge

Georgia’s legal platform.

Download on the App StoreLegal.ge for iPhone

Quick Links

  • About Us
  • Specialists
  • Open tasks
  • Services
  • Laws & Codes
  • Firms
  • Organisations
  • Events
  • Blog
  • Contact

Legal

  • Legal library
  • Privacy Policy
  • Terms & Conditions
  • Cookie Policy

Contact

contact@legal.ge+995 551 911 961Need a lawyer? Find a specialist

Tbilisi, Georgia

© 2026 Legal.ge. All rights reserved.

Made with in Georgia

  1. Services
  2. Real Estate Law
  3. Construction and Development
  4. Construction Contracts
  5. Construction Contract Disputes

Services

0 services available

Loading...

Construction Contracts

Construction Contract Disputes

Who bears the risk of an estimate overrun?

The contractor: on a significant overrun it may claim only the agreed remuneration, unless the excess could not have been foreseen.

What follows from the customer's failure to accept the work?

The contractor may claim compensation of loss, calculated from the duration of the delay, the remuneration and the possible alternative income.

How is the contract ended at the customer's will?

At any time before completion, at the price of compensating the work performed and the loss caused.

What is the limitation period for a structural defect claim?

Five years from the day of acceptance of the work; as a general rule, claims for defective performance must be brought within one year.

4 min·9 Jan 2026

Cost Estimate Overruns and Their Consequences

One of the most common grounds of construction disputes is the overrun of the cost estimate. Article 631 regulates this situation clearly: if the contractor significantly exceeds the approximate cost estimate, it may claim only the agreed remuneration, except where the excess could not have been foreseen in advance. This rule places the risk of overspending on the contractor and obliges it to plan precisely.

Where the cost estimate increases in a way that could not have been foreseen at the conclusion of the contract, the contractor must notify the customer immediately. If the customer terminates the contract because of the increase in the estimate, it is obliged to pay for the work performed according to the approximate cost estimate. A timely and documented notice of the overrun is in this situation the foundation of the contractor's position, and its absence may cost the contractor the entire excess.

Updated: 14 Oct 2026

Legal basis:

  • საქართველოს სამოქალაქო კოდექსი
  • საქართველოს სამოქალაქო საპროცესო კოდექსი