Legal.geLegal.geLegal.ge
SpecialistsCompaniesLibraryBlog
More
AboutPricingContact
LegalTools
Loading accountLog in
AboutSpecialistsCompaniesLibraryBlogPricingContact
LegalTools
Loading accountLog in
Legal.ge

Georgia’s legal platform.

Download on the App StoreLegal.ge for iPhone

Quick Links

  • About Us
  • Specialists
  • Open tasks
  • Services
  • Laws & Codes
  • Firms
  • Organisations
  • Events
  • Blog
  • Contact

Legal

  • Legal library
  • Privacy Policy
  • Terms & Conditions
  • Cookie Policy

Contact

contact@legal.ge+995 551 911 961Need a lawyer? Find a specialist

Tbilisi, Georgia

© 2026 Legal.ge. All rights reserved.

Made with in Georgia

Loading…
  1. Services
  2. Education Law
  3. Education Business
  4. Public-Private Partnerships
  5. School Construction PPPs

Services

2 services available

Education PPP StructuringSchool Construction PPPs
Public-Private Partnerships

School Construction PPPs

What is included in a construction contract?

The object, the scope and characteristics of the work, property rights, the term, remuneration and the manner of termination — Article 21.

Who controls the use of the school?

The infrastructure is used only for the purposes established by the contract; the private partner duly observes the standards.

How is public support valued?

By availability or result-based remuneration, guarantees, grants, land and exclusive rights — Article 28.

What ceiling does the state obligation have?

The ceiling is established by public-finance legislation; the calculation methodology is approved by the Government.

4 min·9 Jan 2026

The Principal Contract Conditions with Construction Specificity

The heart of a public-private partnership for school construction is the contract. Under Article 21 of the Law on Public and Private Cooperation, the contract must contain the principal conditions: the object of the contract, the scope and characteristics of the work to be performed and other issues connected with the public infrastructure or the services to be rendered; the manner of distributing and transferring property rights between the parties; the term of operation; availability remuneration, result-based remuneration or other payments to the private partner; payments to be made by the public partner; and the grounds, manner and consequences of the termination of the contract.

In the construction context this list takes on a concrete technical language: the scope and characteristics of the work comprise the school design, the construction specification and the quality parameters, while the term of operation unites the construction and operation periods. The contract is concluded for a definite term, the principles of determining which are established by a legal act of the Government — which is why the time model of a school project requires an exact breakdown of both periods.

The Use of Public Infrastructure

Article 24 of the law regulates the regime of the built and existing infrastructure: public infrastructure must be used only for the purposes defined by the cooperation contract, unless otherwise provided by Georgian legislation. The private partner is obliged to duly observe the conditions defined by the contract and the standards established for the use of the public infrastructure.

For a school this means that the constructed building must be used only for its educational purpose and its maintenance must meet the established standards. A change of purpose — for instance, converting part of it to a commercial function — must occur in the manner provided for by the contract; otherwise it constitutes a breach.

Updated: 7 Nov 2026