Energy Grid Connection

How long does the connection process take?

Timelines are set by GNERC rules. Standard low-voltage connections take 20-60 days. High-voltage or complex connections requiring grid reinforcement can take several months or even years.

Can I build my own line to the grid?

Yes, usually for high-voltage connections, the user builds the line from their facility to the connection point, while the operator builds the connection infrastructure itself.

What if the operator delays connection?

You are entitled to compensation (penalty) calculated as a percentage of the connection fee for each day of delay. A lawyer can help enforce this claim.

Reading Time

3 min

Published

...

Energy Grid Connection is a fundamental right and, at the same time, a complex technical-legal process for any new subscriber in Georgia, be it a power plant or a large enterprise. This service covers the full cycle of the connection process: from submitting the application to physical energization. Unlike merely drafting an "agreement," the connection service implies process administration, obtaining technical conditions, interacting with the grid operator (GSE, Telasi, Energo-Pro), and, if necessary, resolving disputes at GNERC. Georgian legislation obliges the grid operator to connect a new user if technical feasibility exists, but in practice, groundless refusals, delays, and the imposition of unreasonable costs are common, requiring a qualified legal response.

Lawyers represented on the Legal.ge platform offer full legal management of the grid connection process. Services include:

  • Managing the connection application: Preparing and submitting a complete package of documentation to the grid operator to eliminate formal defects.
  • Appealing technical conditions: If the operator proposes an unfavorable connection point or demands excessive investment in grid reinforcement, the lawyer appeals these conditions to GNERC.
  • Queue Management: In cases where grid capacity is limited (e.g., for solar plants in certain regions), legal battling to maintain or improve position in the queue.
  • Seeking alternative solutions: Obtaining permission to build a Direct Line if connecting to the grid is economically unviable.
  • Imposing sanctions on the operator: If the grid operator violates legally established connection deadlines, demanding compensation (penalties).

Energy grid connection services are particularly relevant in the following situations:

  • A developer builds a new district and needs a high-capacity connection. The grid operator claims the substation is overloaded and demands the purchase of a new transformer at the developer's expense. The lawyer checks the legality of this demand.
  • A solar power plant investor receives a refusal to connect due to "system constraints." The lawyer demands justification and an alternative study.
  • An enterprise requests a change in voltage level (e.g., moving from 10 kV to 35 kV) to reduce tariffs but faces bureaucratic resistance.
  • The grid operator delays installing the meter and registering the subscriber, hindering the facility's opening.

The process is regulated by the "Network Rules" (Transmission and Distribution) and GNERC's resolution "On Fees for New Customer Connection." Legislation clearly defines deadlines and fees for standard and non-standard connections. The grid operator is obliged to develop the grid, although "Deep Connection" costs may legally fall on the user in certain cases. The Law on Energy and Water Supply prohibits discrimination in the connection process.

Collaborating with a Legal.ge specialist saves you time and money. Energy companies often exploit their monopoly position and the subscriber's lack of information. A qualified lawyer ensures that you benefit from all rights granted by law and gain access to the grid under optimal conditions.

Find energy dispute and regulation experts on Legal.ge. Our platform allows you to protect your business interests in dealings with energy giants. Ensure your project is connected to the grid timely and effectively.