Construction Contracts

Construction Defect Claims

When is work deemed accepted?

Where transfer is necessary under the contract or the character of the work, the customer must accept the completed work, and it is deemed accepted if the customer does not accept it within the period established by the contractor.

What happens if I accept defective work without a demand?

Where the defect is known and the customer accepts the work without declaring a demand, no rights of claim arise because of that defect. Known flaws must be recorded immediately upon acceptance.

Who bears the duty to warn?

The contractor must timely warn of poor-quality material, dangerous instructions or other circumstances threatening the work. After the warning, the customer's inaction gives the contractor the right to refuse the contract and claim damages.

Can liability be limited by the contract?

Generally yes, but where the contractor intentionally conceals a defect, the contractor cannot rely on such an agreement: the customer's rights remain intact for an intentionally concealed flaw.

Within what period can a defect claim be brought?

A claim for a defect of performance may be brought within one year, and one concerning a structure within five years from acceptance. With acceptance in parts, the period begins from complete acceptance.

5 min·9 Jan 2026

Construction Defect Claims: The Demand Stage

After a construction flaw is discovered, a dispute reaches the court only when the demand stage has been passed correctly, and it is precisely at this stage that most claims are either lost or gain force. The Civil Code sets several clear rules for this field: the manner of accepting the work, the consequences of accepting with knowledge of a defect, the contractor's duty to warn, the consequences of intentional concealment of a defect, and the limitation periods. Each of these rules determines what the customer may and may not demand, so the preparation of a demand must be fitted to this framework of the law with precision.

Acceptance of the Work and Its Effects

The first question that decides everything in a defect claim is acceptance. Under Article 649 of the Civil Code, where under the contract or from the character of the completed work its transfer is necessary, the customer must accept the completed work. Upon acceptance the customer is obliged to pay the remuneration. The work is deemed accepted if the customer does not accept the completed work within the period established by the contractor. This norm creates mutual discipline: the customer has the right and duty to accept, while the contractor has the right to have the work handed over within the established period and to receive the remuneration.

What Happens If Defective Work Is Accepted Without a Demand

The second rule is the strictest, and it is here that part of the disputes dies. Under Article 652 of the Civil Code, where the defect of the product is known to the customer and the customer nevertheless accepts it without declaring a demand, no rights of claim arise for the customer because of this defect. This means that knowledge of a flaw requires an immediate declaration of a demand: silent acceptance of a known defect kills the claim with respect to that defect. The practical conclusion is simple: every remark is fixed in writing in the acceptance act, and the dispute over flaws not listed continues later.