Subcontractor Security — What Does and Does Not Exist in Georgian Law
Protecting the value of work performed by a subcontractor in Georgian law begins with one important limitation: the institute of an automatic statutory lien, known in the construction practice of other countries, does not exist in the Georgian Civil Code. A subcontractor cannot, by the mere fact of performing the work, obtain a preferential right over the object — security is always established by transaction. The Code gives two real instruments: pledge over a movable (Article 634) and mortgage over the construction land plot (Article 635); alongside them remains the ordinary claim for remuneration. This page teaches the correct use of these three routes.
The practical consequence of this limitation is concrete: a subcontractor's claim without security is an ordinary claim for remuneration — it stands in line with the claims of all other creditors and is satisfied only through enforcement. Establishing security is therefore the most valuable clause of the subcontractor's contract: it takes the claim out of the queue and gives it preferential status.
Pledge Over the Made or Repaired Movable — Article 634
Article 634 provides: to secure his claims the contractor may use the right of pledge over a movable made or repaired by him, where that thing is in the contractor's possession for the purpose of making or repair. This instrument works exactly where the subcontractor's object is movable — equipment, a construction or an item still in his possession. The general regime of pledge is defined by Article 254: the pledgee has the right of preferential satisfaction of his claim from the subject of the pledge ahead of other creditors; the claim is satisfied through realisation of the pledged property or, by agreement of the parties, through its acquisition into ownership; future or conditional claims may also be secured by pledge.
There are two kinds of pledge: Article 255 defines the types — possessory pledge and registered pledge. The practical difference lies in how the preference operates and what demands the security faces towards third parties. The construction of Article 634 rests on possession: the thing must be in the contractor's possession, and it is exactly this circumstance that connects the pledge to the work performed. It is therefore important for the subcontractor to settle the question of pledge before handing over the thing — the departure of the thing from possession often disables the instrument.