Construction Law Advisory — a Legal Audit of the Contract
Construction law advisory is a systematic review of an ongoing or planned construction relationship, without the questions that create disputes. The foundation of this review is the works-contract norms of the Civil Code: Article 629 — under a works contract the contractor undertakes to perform the work and the client to pay the remuneration; and Article 630 — remuneration is deemed agreed even without words where the work is to be expected only for remuneration, and where the amount is not agreed, the tariff or the customary remuneration applies. Advisory builds its question on exactly these two supports: what is in the document and what will remain against the background of the law.
The timing of the advisory also matters: the best format is a meeting held before the contract is signed, when every amendment is still possible; a second useful point is the middle stage of an ongoing project, where the accumulated documentation creates clarity for the second half. A late advisory also has value — but its result is then an assessment of existing mistakes rather than their prevention.
Quality and Cure Control — Articles 641 and 642
The central block of the review is quality. Article 641 provides: a thing is defect-free if it conforms to the agreed conditions, and in their absence if it is fit for contractual or customary use; a different thing or a lesser quantity is also deemed a defect. Article 642 regulates the cure mechanism: where there is a defect, the client may demand supplementary performance; the contractor has the choice — to eliminate the defect or make a new thing, at his own cost (transport, labour, materials), unless this requires disproportionate costs. The audit compares these norms with the document: is the measure of quality described, and is the cure procedure present in the contract?
Handover and Acceptance — Article 649
The acceptance stage is the most disputable point of a construction relationship, and the law regulates it clearly: where under the contract or the nature of the work a transfer is required, the client must accept the completed work; immediately upon acceptance he must pay the remuneration; and the work is deemed accepted if the client fails to take it within the period set by the contractor. The advisory regulates this stage in advance: the acceptance procedure, the form of the acts and the method of recording objections are defined — because exactly this documentation becomes the principal evidence of any later dispute.