The Construction Defect Claim — the Legal Framework
After discovering a construction defect, the client's route is regulated by law, and it begins with the measure of quality. Article 641 provides: a thing is free of defects if it conforms to the agreed conditions; where such conditions are not agreed, the thing is deemed defect-free if it is fit for the use contemplated by the contract or for customary use. Equal to a defect is the case where the contractor makes a thing different from the one ordered or of lesser quantity. This measure decides whether a defect exists at all: first the contract, then fitness for use.
Establishing the measure is an evidentiary question: the contract terms or the technical brief show what was agreed; the documentation of the performed work and the expert conclusion show what resulted. Where the conditions are detailed, the comparison is simple; where they are not, the standard of fitness operates, and determining customary use requires study. Preparing a defect claim therefore always begins with comparing these two lists: what was ordered and what was performed.
Demanding Supplementary Performance — Article 642
After discovering a defect, the first remedy is supplementary performance: where the thing has a defect, the client may demand supplementary performance. The contractor may, at his own choice, either eliminate the defect or make a new thing. For the purpose of supplementary performance the contractor must bear the necessary costs, including transport, labour and materials; however, he may refuse supplementary performance if it requires disproportionate costs. Where the contractor makes a new thing, he may demand from the client the return of the defective thing. This is how the law balances repairability and proportionality.
Termination and Price Reduction — Articles 644 and 645
Where the defect is not cured, the client has stricter remedies too. Article 644: because of a defect of the thing, the client may terminate the contract under the statutory procedure, and in that case the contractor must reimburse the client the expenses connected with the contract. Article 645 offers the alternative: a client who neither accepts supplementary performance after the expiry of the period set for it nor terminates the contract may reduce the remuneration by the amount by which the defect reduces the value of the thing. This is the middle way where the work is not undone at all, but is worth considerably less.